Greenland Road, Hartlepool
Miller Homes & Bellway

Project Overview
Highway improvement works completed under a road opening permit and approved by Hartlepool Borough Council.
DELIVERED ON A LUMP SUM, FIXED COST BASIS
CONTINUOUS LIAISONS WITH RESIDENTS
£0 EXTRAS CHARGED TO THE CLIENT
COLLABORATION WITH ADOPTING AUTHORITY
4 WEEK PROJECT DURATION
IMMEDIATE SIGN-OFF
Works Involved
· Resolved design queries to ensure sign off was successfully achieved first time.
· Grass verge reconstruction.
· Full depth paved footway reconstruction including tactile paving and new kerb lines.
· Areas of cycleway resurfacing.
· Carriageway widening.
· Installation of signage.
· Installation of road markings.

BEFORE

AFTER
Site Challenges
Prior to commencing on site, a level discrepancy was noticed and therefore collaboration with the designer was required to enable successful delivery and remove any potential low spots within the carriageway. The site itself had a narrow working area that limited access, particularly during footway and carriageway reconstruction.
Unforeseeable ground conditions were identified. However, we managed to agree and increase the capping layer depth without hindering the programme, ensuring the works were completed within the road space allocation. Vista’s consult-and-construct approach resulted in this project being signed off first time by the local authority. The scheme was delivered on time, and therefore removed the liability from our clients.
Local Authority Testimonial
Client Testimonial
I would like to thank you and your team for the work carried out on the Powlett Road Roundabout scheme. It was carried out with professionalism and completed in the agreed timescale.
I am looking forward to working with Vista on the next scheme in Hartlepool!”
Chris Roberts
Asset Management Co-ordinator
Hartlepool Borough Council
Local Authority Testimonial
Authority Testimonial
“‘I recently had the pleasure of working with Vista Civil Engineering on a challenging Section 278 project, and I must say that their level of expertise and service is second to none. From the initial consultation to the project's completion, their team demonstrated a remarkable commitment to delivering exceptional results.
The project involved the implementation of Section 278 works to a legacy residential estate. Vista were not only highly knowledgeable but also displayed a deep understanding of highway adoption works. Their ability to navigate the con-straints of the project ensured that the works were completed smoothly.
Throughout the project, the team maintained clear and open lines of communication. They were responsive to our questions and concerns and provided regular updates on the project's progress.
The completed highway works met our expectations in terms of functionality, safety, and durability. It's evident that Vista takes pride in their work and is committed to delivering projects that stand the test of time.
I highly recommend Vista to anyone seeking a company that combines exceptional expertise, transparent communica-tion, and a commitment to sustainable and high-quality Section 278 delivery. I look forward to working with them again in the future.”
Mahesh Ganeshan—London Borough of Sutton
Contact
Get in touch
Thank you for visiting Vista Civil Engineering. If you would like to contact us directly, please email info@vista-civils.co.uk or
call 0330 165 7989
International House
45-55 Commercial Street
London
E1 6BD